Week 8
The machined parts that were ordered came in this week (Figure 1) however, the remaining parts did not. There was a power outage at Drexel and because of this it set back the shipment an entire week. As seen in figures two and three, the parts fit perfectly in the chassis. The parts that did not arrive include raw materials that need to be machined by the team and some fasteners that are required for assembling the pedal box.
|
Fig 1: Machined parts |
|
Fig 2: Close up view of main structure of pedal box resting in the chassis |
|
Fig 3: Distant view of main structure of pedal box in the chassis |