Week 9
The raw materials that we were waiting on as well as the fasteners came in this week so we were able to machine the remaining parts in order to start the assembly. Figures one and two show group members working on the assembly in the Formula SAE room. During the week the chassis was drilled in order to mount the pedal box into the car. By the end of the week the pedal box was all put together. Figure three shows the complete final assembly of the pedal box.
|
Fig 1: Group members working on the assembly |
|
Fig 2: Group marking holes using a transfer punch |
|
Fig 3: Final assembly |
No comments:
Post a Comment